RFP: Johnson Land Bridge Engineering Assessment
Town of Washington, Vermont
Request for Proposals (RFP)
Engineering Assessment of Abutment Walls – Johnson Lane Bridge
Date Issued: August 21, 2025
Site Visit: September 17, 2025 @ 8am
Proposal Due Date: October 7, 2025 by 3pm
Bid Opening: October 7, 2025
Bid Review and contract awarded: no later than October 14, 2025
Project Completion: preferred by May 1, 2026
Introduction
The Town of Washington, Vermont is soliciting proposals from qualified engineering firms for a
comprehensive structural assessment ofthe abutment walls for bridge #1 (gps: 44.10072, –
72.46347) located on Johnson Lane. Both abutment walls experienced erosion and significant
stone displacement as a result of the July 2023 flood. The Town seeks professional services to
determine the structural stability ofthe existing walls and to provide recommendations for
necessary repairs or reconstruction in accordance with current Vermont Agency of
Transportation (VTrans) bridge standards.
This project is being funded through the State of Vermont Department of Transportation and is
intended to provide a long-lasting, weather adaptive, and cost-effective repairs to the structure
that supports the safe passage of low-volume vehicular traffic, including emergency and
maintenance vehicles.Scope of Work
The selected firm will be expected to provide the following services:
Site Inspection & Documentation
Perform a field assessment of both abutment walls.
Document existing conditions with photos, notes, and structural observations.
Structural AssessmentEvaluate the structural integrity and stability of the existing walls.
Ο Assess the extent of erosion and stone displacement.
Ο Determine whether the damage poses an immediate safety risk.Engineering Recommendations
Provide short- and long-term recommendations for stabilization or reconstruction.
Develop recommendations for repair or replacement.
Identify compliance gaps with current VTrans bridge standards.
Reporting
o Submit a written engineering report summarizing findings, including diagrams or
sketches.
Include cost estimates for recommended remediation options.
Present findings to the Selectboard or designated municipal staff as requested.
Proposal Requirements
Interested firms should submit a proposal that includes:
Firm background and relevant experience with bridge assessments, especially those
involving drystone abutment walls.
Qualifications of key personnel assigned to this project.
Description of the approach to the scope of work.
Timeline for completing the assessment and report.
A detailed fee proposal (lump sum or hourly with estimated hours).
At least two references from similar projects.Site Visit
An optional site visit will be held on Wednesday, September 17th at 8am. We will meet at the
bridge, roughly 250′ southwest ofwhere Johnson Lane breaks from MacDonald Road (gps:
44.100588, -72.463691).Evaluation Criteria
Proposals will be evaluated based on the following:
Demonstrated experience and qualifications 25%
Understanding of project scope and proposed approach 20%
Proposed timeline and availability 20%
Cost effectiveness and value 20%
References and past performance 15%
The Town reserves the right to reject any or all proposals, and to award the contract in the best
interest of the community.
Optional Bidder Interview and Evaluation Meeting
Following the submission deadline, the Selectboard reserves the right to schedule an evaluation
meeting and/or to establish a three person committee with representation from the Road
Foreman, Road Supervisor and one additional Selectboard member to evaluate all bids and make
a recommendation to the Selectboard within seven (7) calendar days.
The evaluation meeting, if held, will serve as an opportunity for the Selectboard to:
Ask clarifying questions of one or more respondents;
Evaluate presentations or proposals in greater detail;
Facilitate open discussion on project approach, timeline, and capacity;
Score and compare bids in accordance with the evaluation criteria outlined in this RFP.
Respondents will be notified in advance if such a meeting is scheduled and are expected to make
appropriate representatives available if invited.
Submission Instructions
Submit sealed proposals by October 7, 2025 at 3:00 pm to:
Town of Washington
Johnson Lane Bridge Engineering Study
2895 VT Route 110
Washington, Vermont 05675
Electronic submissions and late proposals will not be accepted.
Qualified small, minority, and veteran-owned businesses, women’s business enterprises, and
labor surplus area firms are encouraged to submit bids. The Municipality is an Equal
Employment Opportunity employer.Contact Information
Questions regarding this RFP must be directed to Road Foreman, Stuart Coburn (802-522-0132).Additional Information
이
All structural assessments should conform to VTrans codes and standards for bridges
The engineer is responsible for safety at the job site.
The selected engineer will be required to comply with State contract provisions.
8.1.23 Hydraulic Study For Johnson Lane Bridge #1 (Appendix A)
Issued by:
Town of Washington, Vermont